Fred and I took a trip out west so had lots of catching up to do at the house when we returned.
During our absence, painters came in and sprayed on the prime coat of paint; ceilings were textured; laminate floor was put down in the kitchen, laundry, and bathrooms; cabinets were installed in the kitchen and baths; and tile was installed around the shower and fireplace. The finish carpenters came in to put in baseboards, trim, fireplace mantle, and many other items. Rain prevented the concrete from being poured for the driveway.
This week so far the finish carpenter completed his tasks and the painters have returned to do their job. Laminate flooring was being put down in the entry and walkway. I met with the closet guy about shelving and the landscaper about plants.
Also furnace was installed - important since it's starting to get really chilly!
Kitchen cabinets and microwave.
Master bath tile.
Painting the fireplace.
Pumpkin on the porch! It's starting to be home. :) Thanks for checking in!